Administratief Akkoord tussen het Koninkrijk der Nederlanden en Bangladesh inzake [...] Planning for Sustinable Water Management (IPSWAM)", Dhaka, 02-11-2003[Regeling vervallen per 30-06-2011.]

Geldend van 10-06-2010 t/m 29-06-2011

Administratief Akkoord tussen het Koninkrijk der Nederlanden en Bangladesh inzake het project " Integrated Planning for Sustinable Water Management (IPSWAM)"

Authentiek : EN

Administrative Arrangement [Vervallen per 30-06-2011]

The Netherlands Minister for Development Cooperation, being the competent Netherlands Authority for the purpose of this Administrative Arrangement, hereinafter referred to as ‘the Netherlands Party’, represented in this matter by Mr A.J.A.J.M.G. Hennekens, Ambassador of the Kingdom of the Netherlands to Bangladesh

and

The Economic Relations Division of the Ministry of Finance, Government of the People's Republic of Bangladesh, being the competent Bangladesh Authority for the purpose of this Administrative Arrangement, hereinafter referred to as “the Bangladesh Party”,

Having regard to the provisions of Article I of the Agreement on Technical Co-operation between the Kingdom of the Netherlands and the People's Republic of Bangladesh signed at Dhaka on 19 May 1977, hereinafter referred to as “the Agreement”,

Have entered into the following administrative arrangement:

Article I. The Project [Vervallen per 30-06-2011]

  • 1 The two Parties shall jointly carry out a project, entitled “Integrated Planning for Sustainable Water Management (IPSWAM)”, hereinafter referred to as “the Project”.

  • 2 The objective of this Project is to strengthen the capacity of water sector organisations, including local level Water Management Organisations, the different offices of the Bangladesh Water Development Board (headquaters and regional/local level) and to a limited extent Local Government Institutions, to responsibly assume their roles as specified in the National Water Policy and the Guidelines for Participatory Water Management.

  • 3 The aforesaid implementation of the project by the two Parties is planned to last till 30 June 2011. This completion date will supersede all other references mentioned in the Administrative Arrangement as the completion date of the project. However, disbursements may be made till 31 December 2011

Article II. The contribution by the Netherlands Party [Vervallen per 30-06-2011]

The Netherlands Party shall make a total maximum contribution to the project as follows:

  • A maximum amount of EUR 7,236,180 will be made available as Technical Assistance through direct contracting by the Netherlands Party;

  • A maximum amount of BDT 318,496,863 will be made available as Financial Assistance to the Bangladesh Water Development Board (BWDB).

  • A maximum amount of EUR 204,200 will be available for a Joint Mid Term Review Mission and for Joint Annual Review Missions.

Article III. The contribution by the Bangladesh Party [Vervallen per 30-06-2011]

The Bangladesh Party shall make the contribution to the Project of Bangladesh Taka 252,500,000 in accordance with the Project Document referred to in Article VII, paragraph 1 of this Arrangement.

Article IV. The Executive Authorities [Vervallen per 30-06-2011]

  • 1 The Netherlands Party shall appoint the Embassy of the Kingdom of The Netherlands to Bangladesh as the Netherlands Executive Authority in charge of the Project. The Netherlands Executive Authority shall be represented, in as far as the daily operations under the Project are concerned, by the Team Leader of the Project

  • 2 The Bangladesh Party shall appoint the Ministry of Water Resources as the Bangladesh Executive Authority in charge of the Project.

    The Bangladesh Executive Authority shall be represented, in as far as the daily operations under the Project are concerned, by the Director DP-III of the Bangladesh Water Development Board.

Article V. Delegation [Vervallen per 30-06-2011]

Each of the Executive Authorities shall be entitled to delegate under its own responsibility, partly or entirely, its duties in connection with the Project to other authorities or organisations. In doing so, the Executive Authorities shall inform each other in writing of any such delegation and of the extent of the delegation.

Article VI. The Team Leader [Vervallen per 30-06-2011]

  • 1 The Team Leader shall be responsible to the Netherlands Executive Authority for the correct implementation of the Netherlands contribution.

  • 2 The Team Leader shall act in close consultation with the Bangladesh Executive Authority and shall respect the operational instructions given by the said Authority to the Bangladesh personnel.

  • 3 The Bangladesh Executive Authority shall provide the Team Leader with any information that may be considered necessary for the execution of the Project.

Article VII. The Plan of Operations [Vervallen per 30-06-2011]

  • 1 On the basis of the Report of the Committee for Reformulation of the IPSWAM Programme, January 2001 (revised version May 2002), hereinafter referred to as the ``Project Document", the Executive Authorities shall formulate by common consent an Inception Report stating the overall approach, the management cycle (reporting and formulation of annual plans), the contribution of either Party, the number and duties of the advisers, their job descriptions, the duration of their stay abroad and a description of the equipment and materials to be made available. The Inception Report will include a detailed Plan of Operations for the first year of the Project. For each consecutive year of the Project, an Annual Plan of Operations will be prepared on the basis of the Project Document.

  • 2 The Annual Plans of Operations shall include an itemized budget of the contribution of either Party, a timetable and lists of equipment and materials to be supplied by either Party, and an Operation Priority Scheme.

Article VIII. Status of the Netherlands Staff [Vervallen per 30-06-2011]

The personnel supplied by the Netherlands Party shall enjoy the privileges and immunities, mentioned in the Articles II and III of the Agreement.

Article IX. Equipment and Materials [Vervallen per 30-06-2011]

  • 1 The provisions of Article IV and V of the Agreement shall be applicable to the import and export of the equipment and materials provided by the Netherlands Party as well as to the status of the said equipment and materials.

  • 2 The imported project equipment shall be subject to payment of Customs Duty and Value Added Tax (CD/VAT etc) by the project implementing agency at clearance stage.

  • 3 Machinery, tools, implements and equipment imported for projects on re-exportable basis will be allowed temporary importation facilities under sections 35 & 36 of the Customs Act, 1969 currently in force in Bangladesh and rules framed thereunder.

  • 4 Any supplies and services received or provided locally under the Project will be subject to domestic VAT etc. as per provisions of relevant acts and rules.

  • 5 The Netherlands Party is in no way under an obligation to pay the Customs Duty or VAT etc.

Article X. Reporting [Vervallen per 30-06-2011]

The Team Leader shall, in close consultation with the Project Director, submit to both Executive Authorities a semi-annual report in English every six months on the progress made in the execution of the Project and on the expenditure incurred by both Executive Authorities. Approval or rejection of expenditures made from the Netherlands contribution is entirely and solely at the discretion of the Netherlands Executive Authority. On termination of the Project, the Team Leader shall submit to all parties involved in final report in English on all aspects of the work done in connection with the Project.

Article XI. Evaluation [Vervallen per 30-06-2011]

The Executive Authorities shall have the Project evaluated annually by a Joint Annual Review Mission. These missions will review the achievements of the past year, thoroughly appraise the Annual Plan of Operations for the coming year, and if necessary propose changes in project activities beyond the one-year period. In May 2005, the Executive Authorities shall have the Project evaluated by a Joint Mid Term Review Mission.

Article XII. Settlement of disputes [Vervallen per 30-06-2011]

Any dispute concerning the interpretation or implementation of this Administrative Arrangement which cannot be settled in consultation between both Parties shall be referred to the respective Governments.

Article XIII. Entry into force and duration [Vervallen per 30-06-2011]

This Administrative Arrangement shall enter into force on the date of signature by both Parties and shall expire at the end of the period mentioned in Article 1, paragraph 3, of this Arrangement or on the date on which the Project has been completed in conformity with the provisions of this Arrangement and of the Project Document, whichever date is the later.

DONE at Dhaka on 2 November 2003 in duplicate in the English language

For and on behalf of the Netherlands Minister for Development Co-operation

SJEF L. IJZERMANS

Sjef L. IJzermans

Ambassador Royal Netherlands Embassy in Dhaka

For and on behalf of the Economic Relations Division of the Ministry of Finance, Government of the People's Republic of Bangladesh

M. TASADDUQ HUSSAIN BEG

Mr. Mirza Tasadduq Hussain Beg

Secretary Economic Relations Division Ministry of Finance